Current Year Petitions

Last Updated: 30-Jul-2020



PRO NumberDatePetitioner(s)Respondent(s)SubjectStatusRemarks
35 of 2020 23-Jul-2020 JBM Solar Power Pvt. Ltd. Haryana Power Purchase Centre Petition seeking orders for reimbursement of amount deposited by the petitioner towards construction... In Process
34 of 2020 09-Jul-2020 UHBVNL and Anr Petition under section 42 of the Electricity Act 2003 read with Regulations 22 of Haryana Electricit... Scheduled for Hearing
33 of 2020 29-Jun-2020 Uttar Haryana Bijli Vidyut Nigam Limited Petition seeking approval of the Hon’ble Commission for Demand Side Management Scheme for Installati... Final Order
32 of 2020 26-Jun-2020 Haryana Power Purchase Centre Application under section 86(1) (b) and section 63 of the Electricity Act, 2003 for approval of sour... Final Order
31 of 2020 26-Jun-2020 Distributed Solar Power Association HVPNL and Ors. Petition under Sections 61, 86(1)(c), 86(1)(e) of the Electricity Act, 2003 read with Rule 3 of the ... Scheduled for Hearing
30 of 2020 25-Jun-2020 Sharad Farms & Holdings Pvt. Ltd UHBVNL & Ors. Petition under Section 142 read with Section 146 of the Electricity Act, 2003 as amended from time t... Scheduled for Hearing
29 of 2020 18-Jun-2020 HERC (Suo Motu) UHBVNL and DHBVNL Implementation of Smart meter project in Haryana Interim Order
28 of 2020 18-Jun-2020 M/s Sukhbir Agro Energy Ltd State of Haryana through ACS, Power and Ors. Petition under Section 62 of the Electricity Act, 2003 and regulation 7 of the HERC (Terms and Condi... Scheduled for Hearing
27 of 2020 11-Jun-2020 M/s Hind Samachar Ltd State of Haryana & Ors PETITION UNDER SECTION 62 OF THE ELECTRICITY ACT, 2003 AND REGULATION 7 OF THE HARYANA ELECTRICITY R... Scheduled for Hearing
26 of 2020 03-Jun-2020 Ananth Solar Power Maharashtra Private Limited HVPNL And Ors Petition under Sections 61 read with , 86(1)(c) and 86(1)(e) and 86 (1) (f) of the Electricity Act, ... Scheduled for Hearing